MTCs Bay Bridge Rail Study
cost estimates initially produced
by consultants
compared with
cost estimates published by MTC
after gross errors and following
[Caltrans] peer-review
Initial estimates included at least $100 million for seismic retrofit and structural upgrades [indicated in red, below] already planned. Post peer-review estimates rose over 400% to $3 billion.
FIRST COST ESTIMATES
DESCRIPTION
(A)
COST
ESTIMATES(B)
AFTER ERRORS
in millions
in millions
San Francisco approaches
Tunnels
$ 24
$ 25
Viaducts
$ 0
$ 0
Continuous spans
--
$ 60
Ramp revisions
--
$ 108
Land or air rights acquisition
$ 0
$ 0
subtotal
Increase
West Spans
Continuous spans
--
$ 40
Suspended spans superstructure
$ 295
$ 744
Deck replacements
$ 100
--
Center anchorage
$ 1
$ 100
SF and YBI anchorage
$ 2
$ 150
Towers/foundations/protection
$ 209
$ 300
Light piers/SF bent/other
$ 1.2
--
subtotal
increase
Yerba Buena Island
Approach from West Spans
$ 4
$ 20
Ramp modifications
$ 0
$ 72
Tunnels
$ 30
$ 45
Approach from East Spans
$ 4
$ 180
subtotal
increase
East Spans
Deck improvements/modifications
$ 15
$ 106
Deck strengthening
$ 15
$ 440
Barriers/restriping
$ 3.3
--
Viaducts
$ 4.25
--
subtotal
increase
Lane closures
$ 50
--
increase
Oakland mole
Fly-overs
--
$ 45
At-grade rail
--
$ 15
subtotal
25% contingency
(W.P.2A.3 only)--
$ 612
TOTAL
$ 758
$ 3,062
percent increase
(+ 403%)
ABOVE COSTS ARE X 1,000,000
N.B. The table is a side-by-side comparison of column (A)first cost estimates produced by consultants for structural modifications necessary to accommodate rail, and column (B) a second set of cost estimates produced by consultants and published by MTC in Working Paper 2A.3. For equal comparison, these two columns reproduce estimates for the hypothetical below option [rail deck below existing decks on the West Span]. In both earlier and later estimates, the below case was indicated as the least costly of three options considered in both earlier and later estimates. The full range of estimates was:
First cost estimates (A) $ 758 million - $ 905 million
Second cost estimates (B) $ 3.06 billion - $ 3.33 billion
Estimates in (A) were produced by consultants prior to a meeting scheduled October 12, 1999 with the Technical Advisory Committee;
Estimates in (B) are from Appendix A [Working Paper 2A.3], Bay Bridge Rail Study, Metropolitan Transportation Commission, Feasibility Study Cost Estimate, published October 22, 1999. Ove Arup and Partners appears at the bottom of Appendix A.
Source: MTC